Offutt AFB runway closure delayed to maximize construction ahead of winter months

The ten-month delay of the runway closure allows for demolition and earthwork to begin before winter. This sets up the program to be in the asphalt and concrete work phase by spring 2021 and wrapping up the needed inspections and Federal Aviation Administration approval to reopen in the twelfth month of work.